Praise report!

We are so grateful, that after almost 2 years, the letter we’ve been waiting for from City Power has finally come through! Thank you for your prayers for this mile-stone moment!

City Green Update | God's Miraculous Provision!

On Sunday 24 November 2024 we shared an amazing update on God’s miraculous provision towards our building project! Watch the video for the update,

Pouring of main auditorium floor!

At the end of October we had a massive milstone moment as we poured the main auditorium floor! We had a moment of thanksgiving to God for this milestone as we laid a Bible in the foundation, praying that City Green will always be a place that brings the Hope of Jesus to many people!

Completing upper level brickwork

In October we completed the upper level brickwork which includes upper breakaway spaces and passages. Facing South, these spaces get beautiful sun coming through the ample glass doors and windows during the day!

Completion of main wall and grass area

In October we completed the main auditorium wall and grass area. This huge walls spans an impressive 30m across and is 14m high! We also completed by raised grass area which is getting greener by the day!

Further progress on main wall and grass area

Further progress on main wall and grass area

Progress on main wall and grass area

Progress on main wall and grass area

Building of upper level spaces

Once slabs were completed, we started building up the South facing upper level spaces.

Bricking up of main backstage wall

After the main backstage slab was completed work began on bricking up the main backstage wall. This is a huge wall and brings much completion to the exterior of the building!

Walls start getting their final colour!

We are blessed to have an amazing colour consultant who helped us choose the final colours for the building. ‘Fog Grey’ is our beautiful colour for all the exterior walls. It has a green undertone to compliment the beauty of the natural area City Green is situated on!

Concrete pour!

14 August was a big and long day as 80 cubes of concrete was poured for all the upper level surfaces!

Raising of grass embankment

While working on the concrete slabs, we also raised to grass embankment. This now creates direct access off the grass onto the top level on the new building!

Priming of the walls

August also saw the priming of all the exterior and interior walls, bringing the buliding to life as we prepped for paint!

First staircase goes in!

In August we loved seeing the first staircase going in, creating direct access to the top level!

Preparation for the upper level concrete slabs

In July work started on the upper level concrete slabs. These slabs will cover the backstage area, the upper level rooms, and the mezzanine walkway inside the building.

Aluminium Glass Doors and Windows Installed

In June all the aluminium glass doors and windows on the lower level were installed. This is a massive milestone!

Plastering of the Entire Building

In June we commenced with the plastering of the full interior and exterior of the entire building.

Laying of Breakaway Room Floors

Through May & June we completed the laying of floors in all our lower level breakaway rooms, foyers areas and passages! The main floor will commence in July.

Installation of Upper Level Containers

In May the installation of all our upper level containers was completed. These containers all create breakaway rooms and form some of the upper level walkway which will go around the entire auditorium!

Brickwork & prep for new containers!

In May a lot of brickwork and prep has been happening for the installation of the new upper level containers to go in! This is a drone shot of the amazing progress that has been made in 11 short months!

Brickwork around the full building

Through April we’ve seen the brickwork go up around the complete exterior in preperation for containers which will close in the entire building.

Brickwork moving quickly!

The brickwork around the structure is going up quickly forming the lower level breakway rooms, backstage walls and more!

Our next package of work kicks off!

In February we kicked off with our next package of work! This package will include all the ground level brickwork, the acquiring and conversion of containers for the upper level, the electrical conduiting in the floor, and the final floor slab!

The roof is complete!

In the first weeks of December we saw the complete roof installed on the structual frame! What a transformation!

The roof is going on!

An exciting few days seeing the roof going up!

Rolling out of roof

In the first week of December the entire roof was rolled out on site for installation.

Super-structure goes up!

During the last week of November we got to witness the structure go up, giving the site a whole new feel as we can now experience the scale of the structure! Certain containers have also been put in position for future upper level break-away rooms.

Super-structure goes up!

During the last week of November we got to witness the structure go up, giving the site a whole new feel as we can now experience the scale of the structure! Certain containers have also been put in position for future upper level break-away rooms.

Super-structure arrives on site!

28 November was a HUGE milestone for the project as all the steelwork for the ‘Super-structure’ (main steel frame) arrived on site. All the work has been prefabricated off-site, and now will be installed on-site! This is the whole structure of the auditorium including the roof, planned to be complete by mid-December!

Brickwork for breakaway rooms

During November a large amount of brickwork was completed for a number of our ground floor breakaway rooms and walkways. This will allow for a number of containers to be installed on top of this brickwork for upper level rooms.

Foundations for stage

In October the foundations and steel work for the stage took place.

Digging of foundations for all the breakaway rooms

In October the digging of the foundations for all the side rooms started.

Did you know that on the ground fall we are going to have 3 breakaway rooms, 2 parent’s lounges, plus store rooms. On the upper level we are going to have 4 breakaway rooms, a board room, plus a hospitality lounge!

Reinforcement & raising of the retaining wall

In September we saw the completion of the reinforcement and raising of the retaining wall (which will be behind the backstage area of the new auditorium). A concrete slab will be built extending from the wall to the new building. This will be the primary connecting point between the old and the new buildings.

(Interesting fact: this retaining wall was previously built to retain an Olympic size swimming pool which was situated on the grass section behind it!)

Continuation of the lower floor surface bed

Through August worked continued on the lower level floor bed, with the fill brought in amounting to over 800 cubes!

Commencement of the lower floor surface bed

At the end of July work started on the lower floor surface bed, giving a good sense of what the layout of the audiroium will look like!

First concrete pour

Friday 14 July 2023 was another mile-stone day as 16 trucks rolled in for our first concrete pour!

The piles are in!

On 7 July 2023, all twelve mini-piles were installed into the foundations.

New Circulation Road Complete

On 28 June 2023 our brand new circulation road was completed and ready to be driven on!

Excavations are progressing daily

In the last weeks of  June the excavations for the foundations progressed quickly in preperation for the piles to be installed in the first week of July!

Foundations have begun

19 June was a landmark day as the laying out of the foundations started, with the digging out of the foundations due to commence later in the week.

More containers

In May, 3 more containers arrived on site. These 12m containers are going to be set in place during the upcoming foundation work, for where they will be used in the future building!
The scripture on the trucks this time was Isaiah 26:12
“Lord, you establish peace for us; all that we have accomplished you have done for us.”

Circulation Road

On Monday 24 April 2023 work began on the relocation of the main circulation road. This is the first of 4 major projects, the second being the foundations which is due to commence mid-May.

Ground Breaking Sunday

On Sunday 23 April 2023 we officially broke ground on the new auditorium! This was an incredibly special moment as we took everyone down after the gatherings to share in communion, pray and celebrate this milestone!

The containers are rolling in

The new auditoirum will include a number of  containers making up some of the upper level breakaway rooms! We will be acquiring containers at the best possible prices as they become available and storing them onsite for future conversion.
The first three containers arrived in April, and the trucks had these 2 scriptures on the front!
Philippians 4:7
And the peace of God, which surpasses all understanding, will guard your hearts and your minds in Christ Jesus.
Ephesians 6:10-18
Finally, be strong in the Lord and in the strength of his might.

We thank God for…

An extremely generous donation of over 3000s/m of carpet which was delivered from Cape Town at the end of March, and will be more than sufficient to carpet our entire new auditoiurm.

If you would like more information about City Green, or would like to enquire about booking one of our venues, please contact hello@cityhope.joburg

Follow what God is doing

CHURCH

 

Latest Messages

Gatherings

Groups

Initiatives

GATHERINGS

 

City Kids

City Crew

City Youth

City Women

INITIATIVES

 

Coming Up

The Institute

Partnership Night

CONTACT US

 

076 660 8525

245 Pritchard Street, Joburg North